ANALIS PENYEBAB DAN DAMPAK KETERLAMBATAN PROYEK MENGGUNAKAN METODE FAULT TREE ANALYSIS DAN EVENT TREE ANALYSIS (STUDI KASUS PROYEK VILA MARC KLOK)

Authors

  • Fatma Nur Janah Politeknik Negeri Bali
  • I Wayan Suparta Politeknik Negeri Bali
  • Yuliana Sukarmawati Politeknik Negeri Bali

Keywords:

Delay, Fault Tree Analysis, Event Tree Analysis, Construction, Factors delay

Abstract

During the construction phase, the Marc Klok Villa project experienced delays due to several factors, necessitating actions to prevent ongoing risks. The Marc Klok project, initially scheduled for completion on December 31, 2023, was actually finished on May 31, 2024, resulting in significant delays. This study was conducted to analyze the dominant factors causing project delays using Fault Tree Analysis (FTA) and to understand the impacts of these delays using Event Tree Analysis (ETA). The findings of this research are expected to serve as additional references for construction industry practitioners to reduce the risk of delays in project execution. Among the six factors contributing to the delays in the Marc Klok Villa project, the most dominant factor was the design drawings. The analysis of the impact scenarios and risk levels associated with the frequency of project delays using Event Tree Analysis indicates that the design drawings have a probability and consequence at the initiating event level with an "Extreme" risk rating

Published

2024-12-30