ANALISIS KINERJA PROYEK VILLA RUMAH RU BERDASARKAN METODE EARNED VALUE
Keywords:
project performance, time, cost and earned valueAbstract
The RU Villa construction project is scheduled be completed within 210 days with a contract value Rp. 9,633,784,501.21.The existence a time limit requires good and mature planning and realization in the field so will affect performance. In analyzing data,the author takes data from the beginning of study, namely weeks 1-39.This study uses a type of quantitative data,the quantitative results will be analyzed, the data collected is based information from direct observation at the time of the implementation of the development project. In data collection, interviews are conducted with sources related to permits use the data as well requesting data, where results of data obtained will be used analysis techniques. Data processing uses Earned Value Method, performance of week 1-12 positive value means the acceleration project completion time, while week 13-39 negative value means late, in SPI value in week 1-12 value<1 means project is completed faster while week 13-39 value>1 means implementation of work is delayed, the cost performance with a positive CV value in week 1-36,CPI value of 1 means cost is still below budget, week 37-39 has a negative value with a CPI value<1 means costs incurred are greater than budgeted costs. So the remaining final time for project completion, which is 544 days from the 39 week of the planned time and the remaining final cost project of -Rp119,299,495.58, value obtained is form a negative value, which means that the estimated cost incurred exceeds the budgeted cost, then the project is declared to have suffered a loss.