IMPLEMENTASI BUILDING INFORMATION MODELING (BIM) 5D PADA PEKERJAAN STRUKTUR TERHADAP PERENCANAAN TIME SCHEDULE DAN BIAYA (Studi Kasus: Proyek Pembangunan Gedung Kantor Camat Kuta Utara)

Authors

  • I Gde Ngurah Pramudya Surya Wijaya Politeknik Negeri Bali
  • I Wayan Suasira Politeknik Negeri Bali
  • I Gede Bambang Wahyudi

Keywords:

isualization, estimation, scheduling, structure, cost

Abstract

The increasing construction development requires construction actors to work faster and more efficiently
with output according to the client's desired target. One of the technological developments in the
construction sector is BIM (Building Information Modeling). The purpose of this study is to implement the
use of Building Information Modeling from the building visualization stage (BIM 3D), planning the work
time (BIM 4D), and cost planning (BIM 5D) in the North Kuta District Office Building Construction
project. The research method used is quantitative descriptive, which is assisted by the Revit 2024
application, Microsoft Excel, Microsoft project, and Naviswork. From the results of the analysis, the results
of BIM-based modeling, especially with the Revit 2024 application, help the modeling process or making
working drawings to be more efficient and accurate. The results of the quantity take off with the Revit
application showed a reduction in the volume of casting work by 2.29%, roofing work by 5.44% while the
reinforcement work increased in volume by 2.98%. The duration of the work is 170.6 ≈ 171 working days
which is 4 days faster than the conventional scheduling method with 175 working days. From the results of
the cost calculation with the implementation of Building Information Modeling, the planned budget is Rp.
3,591,657,446 while the conventional method is Rp. 3,607,082,911 so that there is a difference of Rp.
15,425,465 or a cost reduction of 0.427%