ANALISIS PENJADWALAN PROYEK PEMBANGUNAN GEDUNG PUSKESMAS ABIANSEMAL I DENGAN METODE PERT DAN CPM
Keywords:
Duration, CPM, PERT, Time schedule, ProbabilityAbstract
In the implementation of a project sometimes there are unexpected things that are in
accordance with the original plan. Therefore scheduling is one of the parameters that
become a benchmark for the success of a construction project, in addition to budget and
quality.
205
The project that was used as a research object is the construction of puskesmas
Abiansemal I. The purpose of this research is to know the duration of the project using
CPM and PERT methods as well as the probability of success of the existing schedule of
projects.
From the analysis of primary data can be known the average duration of the project
obtained from the results of interviews to the contractor. From secondary data analysis
can be known RAB, time schedule, drawing plan and unit price analysis. The results
obtained by CPM method are 153 days and PERT is 105 to 150 days